Cost: $/BDT and LCOE
What FRED's cost numbers represent, what's included, what's not, and how to compare them to costs from other tools or contracts.
#What the number means
FRED reports cost in dollars per bone-dry ton ($/BDT). When you see a headline like "$87.40/BDT," that is the volume-weighted average across all contributing clusters in the procurement plan.
For multi-year analyses, FRED reports either the year-1 number or the 10-year levelized cost of energy (LCOE) in $/MWh, depending on which is more relevant to the question.
#What's included
FRED's $/BDT covers the engineering cost components:
- Harvest operations: felling, skidding/yarding, processing, loading. The specific cost varies by terrain class and harvesting system.
- Move-in and mobilization: the cost of getting equipment on-site, amortized over the cluster's harvestable volume.
- Transport: chip truck haul to the facility, using the road network distance from OSRM and the IDW-interpolated circuity factor.
- Equipment overhead: amortized capital cost of the harvesting and chipping equipment, expressed as an hourly cost built into FRCS.
#What's not included
FRED's cost is engineering cost. The following are not included because they are facility-specific, contract-specific, or beyond FRED's data scope:
- Stumpage payments to landowners. These vary by ownership type and contract.
- Permitting costs. Highly site-specific.
- Insurance and bonding.
- Office overhead, admin, and brokerage on top of the operational cost.
- Facility-side costs: receiving, secondary handling, storage. FRED's number arrives at the facility gate.
- Fuel price fluctuations. FRCS uses average diesel pricing. If current diesel is unusually high or low, real costs will differ.
A reasonable rule of thumb: take FRED's $/BDT and add roughly 15-25 percent for the full delivered cost including stumpage, overhead, and contract margin. This is approximate; real contracts have wide variance.
#Cost drivers
The harvest cost surrogate's feature-importance analysis shows the dominant cost drivers in order:
- Terrain class and harvesting system (~65 percent combined). The biggest single determinant.
- Biomass density per acre (~20 percent). Denser clusters amortize fixed costs better.
- Haul distance (~8 percent). Linear effect on transport.
- Cluster size and slope (remainder).
- Treatment type has minimal impact (about 1.1 percent of LCOE variation). A counterintuitive but consistent finding.
#Comparing FRED costs to elsewhere
Reasonable benchmarks for California biomass:
- The cheapest clusters in flat-terrain ground-based regions come in around $40-60/BDT at the facility gate.
- Typical mid-range procurement runs $75-105/BDT.
- Steep cable yarding can reach $130-170/BDT in remote terrain.
- Helicopter operations are typically $200+/BDT and only justified for high-value contexts.
If FRED returns a number well outside this range for a specific location, it's worth asking why. Usually it's a terrain class you weren't expecting or a transport circuity zone that ramped up the haul cost. The justification paragraph will name the driver.