Cost: $/BDT and LCOE

What FRED's cost numbers represent, what's included, what's not, and how to compare them to costs from other tools or contracts.

#What the number means

FRED reports cost in dollars per bone-dry ton ($/BDT). When you see a headline like "$87.40/BDT," that is the volume-weighted average across all contributing clusters in the procurement plan.

For multi-year analyses, FRED reports either the year-1 number or the 10-year levelized cost of energy (LCOE) in $/MWh, depending on which is more relevant to the question.

#What's included

FRED's $/BDT covers the engineering cost components:

  • Harvest operations: felling, skidding/yarding, processing, loading. The specific cost varies by terrain class and harvesting system.
  • Move-in and mobilization: the cost of getting equipment on-site, amortized over the cluster's harvestable volume.
  • Transport: chip truck haul to the facility, using the road network distance from OSRM and the IDW-interpolated circuity factor.
  • Equipment overhead: amortized capital cost of the harvesting and chipping equipment, expressed as an hourly cost built into FRCS.

#What's not included

FRED's cost is engineering cost. The following are not included because they are facility-specific, contract-specific, or beyond FRED's data scope:

  • Stumpage payments to landowners. These vary by ownership type and contract.
  • Permitting costs. Highly site-specific.
  • Insurance and bonding.
  • Office overhead, admin, and brokerage on top of the operational cost.
  • Facility-side costs: receiving, secondary handling, storage. FRED's number arrives at the facility gate.
  • Fuel price fluctuations. FRCS uses average diesel pricing. If current diesel is unusually high or low, real costs will differ.

A reasonable rule of thumb: take FRED's $/BDT and add roughly 15-25 percent for the full delivered cost including stumpage, overhead, and contract margin. This is approximate; real contracts have wide variance.

#Cost drivers

The harvest cost surrogate's feature-importance analysis shows the dominant cost drivers in order:

  • Terrain class and harvesting system (~65 percent combined). The biggest single determinant.
  • Biomass density per acre (~20 percent). Denser clusters amortize fixed costs better.
  • Haul distance (~8 percent). Linear effect on transport.
  • Cluster size and slope (remainder).
  • Treatment type has minimal impact (about 1.1 percent of LCOE variation). A counterintuitive but consistent finding.

#Comparing FRED costs to elsewhere

Reasonable benchmarks for California biomass:

  • The cheapest clusters in flat-terrain ground-based regions come in around $40-60/BDT at the facility gate.
  • Typical mid-range procurement runs $75-105/BDT.
  • Steep cable yarding can reach $130-170/BDT in remote terrain.
  • Helicopter operations are typically $200+/BDT and only justified for high-value contexts.

If FRED returns a number well outside this range for a specific location, it's worth asking why. Usually it's a terrain class you weren't expecting or a transport circuity zone that ramped up the haul cost. The justification paragraph will name the driver.

NOTE
Industry quotes are usually delivered cost including contract margin. FRED's engineering cost will be lower than a delivered quote. The difference is the contractor's overhead and margin, not a modeling error.